Amur Minerals

 

 

Kun-Manie Pre-Feasibility Study

Preliminary Pit Designs

Maly Krumkon Vodorazdelny Ikenskoe
Maly Krumkon
Vodorazdelny
Ikenskoe
Click image to enlarge Click image to enlarge Click image to enlarge

The Company announced the results of an independent pre-feasibility study prepared by SRK on the Kun-Manie project in December 2007:

  • Post Tax NPV (10 %) of $84 million;
  • Annually 4 Mt of ore open-pit mined;
  • Production – a total of 38.2 Mt of ore (at 0.55% nickel and 0.15% copper);
  • 16,000 tonnes of nickel contained in concentrate per year;
  • Initial capital expenditure of $331 million;
  • Total operating cost of $2.51 to generate and deliver a pound of nickel to the nearest railroad.

The pre-feasibility study showed that the project is economic at a nickel price of $7.50/lb. For every $1 above this, $100 million is added to the NPV. At today’s price of $14/lb the NPV is in excess of $800 million.

For more information on the pre-feasibility study, please click here.